Jack M
Moderator
It was the slow season in January . It was supposed to be built week of Feb 10th I changed the order on Feb 3rd . It was built the week of the 17th and at the dealer by the 24th .
I was the 4th on the load and it was a Tube Change ,not a part that had to be ordered .
I went from the Express to the SPS 200 which they most likely have in stock
I was the 4th on the load and it was a Tube Change ,not a part that had to be ordered .
I went from the Express to the SPS 200 which they most likely have in stock